Archives

Home / Guardian Portfolio

Publich Procurement for Renewable Energy

Client: German electric power grid company

Projekt size: 800 Milllion Euro

Task: Tendering and negotiation of construction contracts for underground DC power cable

Targe: Evaluate commercially and technically suitable suppliers, finish project in time, avoid claims.

Project details: Public procurement according to EU Laws and SektVO in Germany. Construction works for 700km DC Power cables from the North Sea to Bavaria split in 10 sections. My responsibility was the tendering, the negotiation, and the award of 4 of those sections. Overall project size will likely exceed EUR 15 Billion.

Outcome: Award to internationally recognised construction companies. Maintaining a certain flexibility in the schedule while reducing claims risk to a  minimum.

 Topics: Public produrement, SektVO, civil works (Tiefbau), renewable energy.

Claims Defense

Client: Large International Pharma and Life-Science Company

Contract size: 21 Million Euro

Dispute: Contractor submitted an unsubstantiated 5.6 Million Euro claim threatening to delay the project if not paid in full.

Targe: Project shall not be delayed, reduce claim as much as possible.

Project details: EPC contract for brownfield project including civil works and all technical systems and plants. Tie in was planned during a general plant shutdown, time was  of the essence. Contractor submitted an unsubstantiated claim for additional works and acceleration measure in the amount of 5.6 Million Euro 3 month before completion threatening to delay the project by 3 months if not agreed to. Contractor severely underestimated the works initially and tried to turn a lump-sum contract into a reimbursable contract for which contractor claimed for each hour worked.

Outcome: Dispite the brute-force behaviour shown by the contractor I still managed to reduce the claim from 5.6 Million Euro to 3.5 Million Euro. The main drives for this success were the identification the contractors lack of entitlement, the lack of actual evidence of employer risk events, the identification of contractor risk events, contractor wrongdoings, and contractors failure to cover the complete project scope in a professional manner.

 Topics: Claims defense, schedule analysis, condition precedence, lack of contractual entitlement.

Above picture is only a graphical representation

Public Tendering Services

Client: Large International Oil and Gas Maintenance Company

End-customer: National Oil Company in Romania

Contract size: 230 Million Euro

Project details: Tendering consultancy for large scale oilfield operations and maintenance contract. Contract duration 8 years, overall tender volume approx 1.8 Billion Euro of which I managed to win contracts  of 230 Million Euros.

 

Topics: Pre-qualification, developing tendering strategy in close cooperation with international HQ, perform site surveys, estimate final tender price, risk assessment, HSEQ related issues. Mobilization of execution team, implementation of maintenance and operations strategies, takeover of fixed and mobile assets, takeover of maintenance and operations personnel (around 1400 people).

Main target: Winning of large scale oilfield operations and maintenance tender, implementation of novel strategies and technologies (e.g. CMMS), service improvement, improvement of plant reliability and uptime.

Above picture is only a graphical representation

Tendering of large EPC Projects

Client: Large International Oil and Gas Company

Contract size: Two projects each around 40 Million Euro

Project details: My tasks here were related to the tendering of two refinery EPC projects

 

Topics: Developing tendering strategy, pre-qualify potential bidders, create tender documents including contracts, harmonizing scope, tender, negotiate, award.

Main target: Evaluation of the most economical solution and award to the best bidder with key focus on HSE, quality and delivery time.

Above picture is only a graphical representation

EPC/EPCm Contracting Strategy

Client: Large International Oil and Gas Company

Contract size: Several hundred Million Euro

Project details: Developing strategy to handle future projects with EPC/EPCm contracts instead of time and material. The strategy change was initiated in order to reduce cost and risk while increasing financial planning accuracy.

 

Topics: Selection of appropriate contractors, pre-qualification, developing EPC/EPCm contracting strategy in close connection with PM and business team.

Main target: A strategy to award future projects on EPC/EPCm basis instead of a historically grown „time and material“ basis in order to achieve better cost planning accuracy and reduce risks.

Above picture is only a graphical representation

Implementation of Variation Order Management

Client: Large International EPC

End customer: National Oil Company

Contract size: USD 550 Million

Project details: Electrification for LNG Terminal

 

Topics: Implementing best practice variation order management system.

Main target: Early detection of variations, proper substantiation, contractually conform notification, final negotiation training.

Outcome: Training with project stakeholders including engineering, project management, procurement, and execution. Implementation of processes and a central variation order tool.

Above picture is only a graphical representation